Peak Shifting

Peak Demand Shifting: Store and Shift Capacity method

The Store and Shift Capacity (SASC) sub-method encourages households and small businesses to create the capacity to shift electricity demand away from peak periods.

Read below for more information about:

  • activities under this method
  • activity requirements
  • requirements for equipment you can use
  • fact sheets you need to give your customers.

Eligible activities

The PDRS Rule includes 4 Activity Definitions under the SASC Method relating to installing a new behind the meter battery energy storage system. The table sets out each of the activities, the battery sizes allowed and the commencement dates.

Activity Building types/uses Battery sizes (kWh)
BESS1 Single dwelling, small business, government owned and managed buildings 2-28
BESS3 Apartment buildings with at least 4 dwellings 20-200
BESS4 Small and medium businesses 20-200
BESS5 Commercial and industrial businesses 200-30,000

See the PDRS method guide and PDRS Rule for more details.

Activity requirements

Batteries installed under the SASC method must meet SASC-specific requirements set out in clause 8 and Schedule C of the PDRS Rule. 

Refer to the PDRS Method Guide to understand battery activity requirements under the PDRS Rule.

A minimum payment per implementation is required. See the Upgrade costs page for more details. 

Accordion group

Summary of planning approval requirements

Division 4 of the Transport and Infrastructure State Environment Planning Policy (SEPP) includes planning requirements for solar battery systems proposed in NSW. The SEPP defines a solar battery system as a battery system designed only for the purposes of the storage of photovoltaic solar energy generated from a solar energy system. 

Exempt development

Subsection 2.41(5) provides that development for the purposes of a solar battery system is exempt development (i.e. no planning approval required) if the requirements in that subsection are met. These requirements include that the system cannot store more than 20kWh of energy and the development does not result in the installation of more than 1 system.

Complying development

A complying development pathway exists where the maximum kWh storage capacity of all solar battery systems installed on the site does not exceed 100kWh in a prescribed residential zone, or 200kWh if not in a residential zone. This pathway provides a streamlined approach for eligible medium sized battery systems, avoiding the need for a development application provided the complying development requirements are met. Those requirements are set out in subsection 2.39(2C) and Codes SEPP section 1.17A.

Development application

If a proposal cannot meet the requirement for complying development or exempt development, development consent or a modification approval is required. A development application (DA) or modification application (MOD) must be submitted to the relevant authority (usually the local council). Contact the relevant council for more information on the required process.

Applying for planning approval through the NSW Planning Portal

Where a solar battery system proposal is not exempt development, an applicant can seek planning approval through the NSW Planning Portal. This approval is in the form of a complying development certificate, development consent or modification approval. Approval is typically obtained from council or a private certifier. In the Portal’s application form, an applicant could choose ‘Erection of a new structure’ for a proposed standalone solar battery system. General support for this application process can be found here.

For questions about the Portal please use the Department of Planning, Housing and Infrastructure enquiry form. For questions about the SEPP requirements for solar battery systems or batteries that don’t meet the definition of a solar battery system, please contact the SEPP team at tisepp@dpie.nsw.gov.au.

Fact sheet requirements

ACPs or their representatives must give a fact sheet for BESS1, BESS3 and BESS4 to the customer with the quotation for the installation of a battery.

ACPs must keep records as evidence of providing the fact sheet. Auditors will check the fact sheets have been provided during audit.

More information about the PDRS and calculation methods