Individual liable demand is calculated based on the liable acquisitions on each of 4 peak days in the peak demand reduction period.

The 4 days have the highest maximum demand for megawatts of electricity during the compliance period (1 November – 31 March). They are identified based on:

  • 5-minute interval data published by AEMO
  • the highest electricity demand at any time during the day, not just the peak period between 2:30 and 8:30 pm AEST.

The Scheme Regulator will nominate and publish the 4 peak days on this page by 30 April after the end of the compliance period.